4.3 THE DESIGN BRIEF
4.3.1
The are 3 steps to achieving a ‘certified design’. The first step is to ensure a design
brief is prepared.
Step
Document
Action
Clause
1
Design Brief
Issued by TWC to TWD 13.2 [All Categories]
2
Design Certificate
Issued by TWD to TWC
13.7.5 [Cat (1)(2)(3)]
3
Design Check Certificate
Issued by TWDC to TWC
13.7.5 [Cat (1)(2)(3)]
4.3.2
The PC’s TWC is responsible for ensuring a design brief is prepared which adequately
covers the actual site conditions.
4.3.3
In relation to other contractors, the PC’s TWC should:
4.3.4
The SC’s TWC is responsible for ensuring a design brief is prepared which adequately
covers the actual site conditions that have no adverse effects on other works that
they may not necessarily be responsible for.