3.2 CONTRACTURAL INTERFACES
3.2.5
In relation to temporary works the principal contractor has specific responsibilities.
Some are shown below.
3.2.6
There are many combinations of organisations that can be involved in temporary works.
Each have different contractual arrangements from project to project but the overarching principle is that the PC’s TWC has overall responsibility on site.
figure 1 – typical contractual relationships