5.5 TAKING TEMPORARY WORKS OUT OF USE
5.5.7
The temporary works implementation plan and temporary works register should
specify who is authorised to issue the permit to take out of use/dismantle/unload.
5.5.8
The final verification checks or ‘sign off’ should be undertaken by an authorised person.
The following table identifies who should issue the permit based upon the
implementation risk classification.
Figure 1 – who can authorise a permit based upon implementation risk
classification
Who can issue the permit?
Risk
Classification
PC TWC
TWC
TWS
VERY LOW
Yes
Yes
Yes
LOW
Yes
Yes
Yes
MEDIUM
Yes
Yes
No
HIGH
Yes
No
No
Version 2 © mytemporaryworks 2023 | The control of temporary works – procedural guide