BRITISH STANDARD
14.1.8
Prior to bringing temporary works into service a final inspection should be carried out to verify
that it has been constructed in accordance with the requirements of the design and any subsequent
approved modifications. The results of these inspections, together with any requirements for
improvement, should be recorded by the appropriate person as allowed by the implementation plan.
For complex or innovative designs consideration should be given to an inspection by the TWD.
NOTE
14.2
14.2.1
14.2.1.1
BS 5975:2019
It might be necessary to carry out inspections of the temporary works at points during assembly/erection.
Loading and unloading temporary works
Loading (bringing into use)
As a means of exercising control over bringing the temporary works into use a formal procedure for
giving permission to load, or proceed to the next stage in the implementation sequence should be part
of the implementation plan.
NOTE In simple cases a single