BS 5975:2019
t)
BRITISH STANDARD
ensure that any instructions from the PC9s TWC in connection with any identified discrepancies
in the temporary works have been rectified to the satisfaction of the PC9s TWC;
u)
ensure that any agreed changes, or corrections of faults, are correctly carried out on site;
v)
ensure that during use of the temporary works all appropriate monitoring and maintenance is
carried out;
w) ensure a permit to load or proceed (bring into use) after a final check, which is satisfactory, is
issued by either the PC's TWC, TWC or TWS (see 14.2.1);
x)
y)
z)
ensure that a permit to unload or proceed (take out of use), the temporary works is issued, when
it has been confirmed that the permanent structure has attained adequate strength and/or
stability, by either the PC's TWC, TWC or TWS (see 14.2.2);
register or record the drawings, calculations and other relevant documents relating to the final
design of their temporary works and, where required, submit to the PC9s TWC;
ensure that a documented safe system of work is in place and implemented for the dismantling
of any temporary works;
aa) ensure that any relevant information for the health and safety file is transmitted to the
PC9s TWC; and
bb) ensure that any appointed TWS is operating in accordance with the correct approved procedure.
12 Temporary works supervisor
12.1
General
The TWS should be aware that the PC9s DI defines the PC9s TWC lines of responsibility in relation to
each contractor9s TWC and/or TWS, which is employed on the site, using Figure 2 and Figure 3 for
guidance (see 5.1).
12.2
12.2.1
Role of the TWS
The TWS, where appointed, should be responsible to the PC9s TWC or TWC as appropriate. The
TWS should assist the PC9s TWC or TWC, as appropriate, in the supervision and checking of the
temporary works.
NOTE The line of responsibility is appropriate to the organization making the appointment and whether the
organization is approved to manage their own temporary works.
12.2.2
12.2.3
A TWS should only be authorized to issue a permit to proceed, e.g. load (bring into use) or unload
(take out of use), if the DI of their organization and the PC9s TWC are satisfied that:
a)
an individual TWS is competent and has been given the appropriate authority in respect of that
individual; and
b)
the risk classification (see 6.1.3 and Table 1) identified is low or very low.
The role of the TWS is to provide on-site support to the PC9s TWC or TWC for the control of temporary
works; as such the TWS should not be responsible for any design or design checking of temporary
works but should be responsible for the implementation of the PC9s or contractor9s procedure for the
control of temporary works.
NOTE This exclusion also covers the determination of specific loads; assessment of load paths; engineering checks
of any kind; determination of foundation capacity, etc.
12.2.4
The appointment of a person as TWS should not preclude them from carrying out design or design
checking if they are considered competent (see 5.2.1, 8.4.1 and Table 2).